Cameron Street Bridge Project Behind Schedule
By 250 News
Wednesday, December 03, 2008 04:00 AM
Prince George, B.C.- The Cameron Street Bridge project is now 6 months behind schedule. There will also be higher costs, but the exact dollar figure is not yet known.
That was the information delivered to the new Mayor and Council last night.
Councillor Brian Skakun wanted to know what recourse the City has, seeing as how the contractor had bid the project with the understanding it would be completed by the end of the year. The project is now under the process of "dispute resolution". If that fails, there is a possibility of bringing in an arbitrator, and it is possible there could be penalties levied for failure to deliver.
"Are these delays going to cost the tax payers more money?"asked Councillor Brian Skakun. The short answer is, yes. Bill Gaal, Superintendent of Operations says "In any contract there are often extras and they would be a moderate range, not an excessive range." But he couldn't put any details before Council on just how much more the project will cost. He was not able to say how much is “moderate”.
In his report , Bill Gaal, Superintendent of Operations says the demolition work has taken longer than expected. There has been plenty of talk about other issues including, waiting for permission from the Department of Fisheries and Oceans to remove some trees and then there’s the rumour about the steel that was delivered not being the correct type and some of the delays were blamed on the weather.
As for North Nechako/PG Pulpmill Road, that work (development of a roundabout) is on hold until the spring. Maintenance of the gravel surface is required throughout the winter and the contractor is responsible for that maintenance.
Councillor Cameron Stolz wanted to know the standards by which the contractor must keep the gravel road. There had been numerous complaints about the condition of the road at the north end of the bridge.
Councillor Murry Krause says the condition of the road is impacting how people get to and from work, "We have got to make sure people can transit safely and effectively to and from work, so we will have to work on getting that from the contractor and failing that, we will have to take it on ourselves." Gaal says the contractor is supposed to maintain the road to the level of City of Prince George gravel road standards.
River Road is paved from the Overpass to the end of the islands adjacent to Brink Forest Products. The remaining work along Cameron Street includes final placement of road base gravels, asphalt paving, landscaping, lighting, and signage. This work on Cameron St. will take place next spring.
The final culvert along the Brinks Forest Products frontage has been installed which will address the drainage issue along the front of this site. The completion of the driveway reinstatement will take place next spring. There will not be any more work completed in the River Road area this construction season.
The Cameron Street bridge has been closed for three years since it was declared unsafe.
Previous Story - Next Story
Return to Home
Hmmmmmmmmm, are these standards, better than our paved road standards? The road conditions at the north end of the "old" Cameron Street Bridge, are no worse than a lot of streets we have to drive on to get to work Mr. Krause, ever think of that?? Oh seasoned council member!
Shouldn't throw rocks, when you live in a glass house!