Cameron Street Bridge Concrete Questioned
By 250 News
Tuesday, April 07, 2009 04:01 AM
.jpg)
Prince George, B.C. – The Cameron Street Bridge won’t likely be ready for use until at least the end of July.
That was the final line in the report presented to Council this evening from the Operations Manager, Bill Gaal.
But it was Councillor Brian Skakun who wanted more information on the state of the concrete poured as caps and “wing walls for the new bridge. It is his understanding there are cracks and some portions may have to be redone.
General Manager of Development Services, Bob Radloff says there were some issues with the concrete,but the problems have been addressed and corrected. He also said the bridge piers will be thoroughly inspected for safety before there will be any final approval for the bridge to be used.
There is an issue with cost over runs on the construction, and although asked if it was known just how much those over runs were, Radloff didn't give an amount, saying instead the contract provides processes to deal with increases in costs and they are following those processes. Radloff also said the delays in construction were in part the result of "Third party influences".
Gaal’s report outlines the remaining work as follows:
- The new steel girders are now in position over Pier #1 (south shore) through Pier #5 (north shore).
- The 28m Heritage Span has been moved to the City’s 4th Avenue works yard until a new home can be finalized
- Construction will now proceed into the securing of the girders to Pier #3, and preparation for the placement of the precast concrete deck panels.
- Once the deck panels are in place, installation of rebar will begin in preparation for the concrete deck pour.
- It is expected the rebar work will be completed in May with the concrete deck poured by the end of June 2009.
- The concrete jump spans (north & south) will also be formed and poured following the deck work.
- The north concrete wing walls are being constructed prior to the onset of the spring freshet.
- The construction of the watermain is also scheduled to commence prior to the spring freshet (estimated to start by mid April).
Then the focus will be on building the roundabout at the north end.
The roundabout still needs to be brought to sub-grade elevation, catch basins &
electrical fixtures require installation, then the crush base will be placed, concrete curb & gutter and sidewalks will be installed and preparation for, and paving can then take place.
Previous Story - Next Story
Return to Home