Rupert Port Progress
By 250 News
Prince Rupert Port Construction (photo courtesy Prince Rupert Port Authority)
The construction of the Prince Rupert Port is moving right along, with the Port Authority saying a major milestone has been reached.
The completed installation of the 90 concrete-filled steel piles is considered the most complex and difficult part of the construction project. The 120-foot piles have been successfully installed by the wharf contractor, Western Industrial Contractors ( of Prince George) and Fraser River Pile & Dredge . The piles are the foundation for the new container berth.
The container berth is said to be nearing the half way mark of its construction.
The three giant cranes are expected to arrive in July.
On the land side, Prince Rupert Terminal Contractors has completed 65 per cent of the site preparation for the intermodal yard and 50 per cent of the underground utilities. The container port is expected to be up and running in the fall of 2007.
Phase one has yet to be completed, and phase two is getting underway. Consultation with First Nations has begun and Jacques Whitford Environmental Consultants have been hired to conduct the environment assessment.
The idea is to have all the plans in place for the expansion as soon as the first phase is operational. The projected completion date of the 150-acre Phase 2 terminal is late 2010.
Previous Story - Next Story
Return to Home
??????
I am very curious about what this means. Consultation about what? Environmental assessment of what? The port construction is well underway with the pilings in place and the cranes ordered.
What on earth are they consulting about at this late stage and what environmental assessment is being conducted at this late stage?