Colmar Wins Bid for Sewer Extension Job

Tuesday, June 12, 2012 @ 3:45 AM
Prince George, B.C.- Colmar Construction has been awarded the contract to build the sewer extension on Boundary Road.
 
Of the three bids received, Colmar’s was the lowest, at $1,633,445.00 not including taxes. That amount was still above the budgeted amount of $1.6 million so, two optional elements were removed from the project’s  scope.  
With the options of fiber optic ducting and pull boxes removed, Colmar came back with a revised tender of $1,548,831.00.
 
It is anticipated the work will take 14 weeks to complete and will start  in mid July.

Comments

A lot of neighborhoods in PG having been paying municipal taxes for decades and still have no city sewer services. Hart Highlands for example. Yet a road to nowhere for a hypothetical development gets $1.6 million in new sewer infrastructure… to go with the tens of millions already spent on the project.

Its all about priorities in PG.

Comments for this article are closed.