Project manager Tony Bennett at left, points out details of 4 laning Highway 97 south of the Simon Fraser bridge while project engineer, Tim Stevens looks on.
Prince George, B.C.- Work is underway on the next phase of the Cariboo Connector from the Simon Fraser Bridge to Sintich Road on Highway 97 south.
Project Manager Tony Bennett says that stretch of highway will be four laned and there will be some changes to the intersections.
The first intersection, at the old weigh scales, will hopefully have dual left turn lanes on to highway 97 from the BCR site. That will depend on the Ministry of Transportation securing a piece of the property on the south west corner of the highway.
There are some real challenges on the stretch of roadway from the Continental Way overpass to Sintich Road as the east side of the highway is up against a very steep hill. Bennett says there is some more engineering design work being done on that section to see what the design will eventually look like. It could involve a retaining wall.
All in all, he expects the tender for the 5.5 kilometre project to cost about $27.5 million.
The project is expected to go to tender soon and will get underway this fall, shut down for the winter, and resume next spring with a completion date of August 2009.
The plan calls for a four laning of the highway to Sintich Road, then tapering it back to two lanes. “Eventually there will be traffic lights at Sintich Road” says Bennett. He also says the highway lighting will be removed and a median added.
Bennett didn't have any answers as to how the Ministry of Transportation will deal with the high number of collisions involving wildlife along the stretch of highway from Continental Way to Sintich Road.
Project engineer Tim Stevens says fencing doesn't do any good as it only forces the wildlife to bunch up at opposite ends of the fence and cattle guards are not practical.
This section of the Cariboo connector will evetually be four laned to the new weigh scales at Red Rock, but the timing of that project has not yet been determined.
It is all part of a master project to have highway 97 four laned between Prince George and Cache Creek.