Cameron Street Bridge To Be Ready Mid August
By 250 News
Thursday, April 23, 2009 12:18 PM
.jpg)
IDL's Noel Knapp points out to Mayor Dan Rogers how the concrete slabs will be laid over steel girders
Prince George, B.C.- August 15th, mark that on your calendar, that is the date the IDL construction crew has set for the completion of the Cameron Street Bridge.
The President of IDL, Dennis Schwab, told media and Council members this morning that while the contract called for completion of the bridge by December 31st of 2008, there were several reasons for the delays. “The awarding of the contract was delayed because of funding issues, then there were permitting issues which took two months.” Those permitting issues had to deal with Ministry of the Environment and the Department of Federal Fisheries. IDL wasn’t given notice to start the project until late May and by the time the permitting issues had been dealt with, the window for construction was rapidly closing.

“That meant it would be too cold to pour concrete” says Schwabb.
(at right, concrete slabs with re-bar, will be placed on the steel girders, then new concrete poured over top)
There were some other issues as well. When the permits were granted, the project did not allow for a temporary bridge to be built along side the existing structure, “It makes it a slower process to work off an existing structure” says Noel Knapp of IDL. Knapp also says there was a construction expansion of one of the piers ( the pier at the furthest north of the bridge) “The process called for us to move steel girders out ( launch) as we removed the old structure. The original piers did not contain steel reinforcing rods, so the pressure of pushing the steel girders caused a construction joint to appear. It disappeared once the pressure was removed, and we have sealed it so there won’t be any moisture getting into that joint causing any freeze-thaw damage.”
While the contractor has indicated there are some cost over runs, Mayor Dan Rogers says the City has not agreed to any cost over runs at this point. “Those discussions are on going” says Mayor Rogers who adds he does not expect any over runs to be “substantial” which he defines as being in the millions. The contract offers a process for discussing cost over runs, arbitration is included in that process, but the Mayor says they are not at that point.
While the new completion date is August 15th, the Mayor is hopeful that can be trimmed “There have been some issues, but I would hope the timeline can be reduced somewhat.” Rogers says he was not surprised to hear the project was 8 months behind the original schedule, “Anyone who looked at what was going on, could see things were not likely to be completed by the end of last year.” IDL says it advised the City last September about the delays, but that information was not made public until January of this year. When asked why it took so long for that information to be released, Bob Radloff, General Manager of Development and Operations said “The Mayor, (Colin Kinsley) was the spokesman for the City.” Radloff also says he only ever stated that the contract called for a completion date of December 31st, 2008.
With today’s tour taking longer than expected, Radloff asked if Opinion 250 would include that information in this story, so here it is, the tour added a further 20 minutes to the construction of the bridge.
Previous Story - Next Story
Return to Home