Rural Road Projects Outlined
By 250 News
The province has announced it’s sealcoating schedule for the Prince George region.
33.6 kilometres of rural roads in the area will be sealcoated between June 15th and the end of August
Work is scheduled to begin on June 15 and is expected to be completed in late August. The contract is worth $1.4 million
Here are the roads ( or portions thereof) which are on the to-do list:
Shelley Road Area North Kelly Area Cluculz Lake Area
Highplain Road Hubert Road Lloyd Drive
Gleneagle Road Hubert Road Marsolais Drive
Pineridge Road Nightingale Road Velvet Road
Grassland Road Meadowlark Road Tapping Road
Lea Road Eaglecrest Road Sunny Slope Road
East Perry Road Knoedler Road Meier West Road
Emile Crescent Side Roads (7) off of Meier West Road
Alice Road Meier East Road
Spiritwood Road Gill Place
Edoidge Road Meier Sub Road
Louis Road
Homestead Road