Prince George, B.C. - IDL Construction has begun work on the new Cameron St Bridge. The new two lane bridge plans were sent out for tender on February 18th- 2008.
That tender document shows that the berm now in place on River Rd will remain in place at the height of 5.722 meters, which is 2 meters higher than the old pavement and exactly two meters higher than the old 200 year flood plain level.
Assuming that the plan for the new bridge could not be developed in a few days, that would mean the new height for River Rd had been decided before a January 21st meeting was told that the City would embark on a flood study in the City.
"Currently, we're working...to get agreement on Terms of Reference with the province, and also negotiating funds for the province to provide for this service," says Bob Radloff. He says the study will review the risk of flooding to Prince George residents -- which could possibly lead to the redefinition of flood levels -- assessing flows, and assessing influences on those flows.'
"We're also looking at looking at solutions as part of this -- long term solutions, all solutions," says Radloff, "This includes issues like removal of sediment, if that is presented as a possible solution, permanent works -- which include dikes and pumps -- and land-use change, as well."
Manager of Long Range Planning, Grant Bain, says "Part of the scope of the study will be to identify what the new 200-year flood plain level is and the flood construction level." Bain says, once that's determined, it will be contained in a new bylaw, the flood plain mapping would be changed accordingly, and it would be enforced during the development permit stage.
The process to determine the new flood elevation level could take seven months. Radloff says there will be opportunities for public input from interested residents and businesses during that period.
On January 13th Premier Campbell, touring the flood damage was asked who was going to pay for the removal of the River Rd Berm. He replied the province and the city were working on seeing who will pay. Were the plans for the Cameron St Bridge being drawn at that time?
Was it the intent of the City to build River Rd to a new flood plain level and then seek approval for a new by law?
That by law could mean that land and buildings as far west as Northern Hardware on 3rd, would fall under the new flood plain, substantially reducing their value. The area along 1st would also be also be affected.
On April 6th-2008 Opinion250 received the following response from City Manager Derek Bates as to who had ordered that the Berm on River Rd remain in place.
The Provincial Emergency Program made it clear it had not made such a request, and the Ministry of the Environment passed along this response:
Ben, Derek Bates with the City is your contact for this. I believe he has provided you with the link to the City’s decision. This is the information Bates provided to the Ministry Of The Environment
"On December 31st and January 6th, river water levels exceeded the 200 year flood plain levels and in response the Emergency Operations Centre decided to construct earth berm diking in the Ongman Road and River Road areas and in some key areas, during the peak of flooding.
The River Road berm will stay in place until a permanent solution has been devised which is dependent on the long term study that is currently being negotiated between the City and the Province. The berm was a City street (River Road) which has been raised and is built to current Transportation Association Standards, and is considered safe."
This would suggest it was the Emergency Operations Centre which made the decision to construct the “berm” and that it is the City’s decision to keep it in place, not just until after the spring freshet, but until the long term study has been completed which would mean, the raised River Road would be in place until the spring of 2009.
That response came more than 1 ½ months after the drawings for a new bridge and the elevation for River Rd had been drawn and sent out for tender.
Critics of the raising of River Road had argued from day one that the intent was not to build flood protection , but to raise River Road for access to the new Cameron Street Bridge. At the time, (March 27th) Opinion 250 put that question to the Asset Management and Downtown projects Manager, Frank Blues, who said the new Cameron St. Bridge would not require River Rd to be raised.
Opinion250 has asked three City Councilors what they have to say about the process and have been informed that they were not aware of the tender or the new elevations.
What bonehead actually made the decision?? Should be strung up by their shoelaces and used as a pinata!